Application notice: Georgetown Gold Mine
Resource activity: Mining activity relating to a mining lease
It is advised that Georgetown Gold Mine has lodged an application for a major amendment to an environmental authority and a PRCP schedule in accordance with the requirements of the Environmental Protection Act 1994. The environmental authority and PRCP schedule being amended are EPML00899813 and P-PRCP-100633313_V1.
The application relates to the construction and operation of a three-metre lift of the existing tailings storage facility (TSF) at the Georgetown Processing Plant. The proposed lift will increase the storage capacity of the TSF to support the continued operation of the Project. Upgrades to the facility are also included as part of this application, aimed at modernising the operation, monitoring and maintenance of the TSF in accordance with current engineering and regulatory standards.
The resource activity is proposed to occur on the following tenure(s): ML3409, ML3358, ML3374, ML3540, ML3548, ML3591, ML30192, ML30193, ML30195, ML30196, ML30201 and ML30203.
The application documents for the project consist of the Notice of Change to Amendment Application, Environmental Authority and Progressive Rehabilitation and Closure Plan Supporting Information Report, the Information Request Notice and response to the Information Request Notice.
Application documents may be inspected or accessed at https://savannahgoldfields.com/georgetown-gold-project/ and at Current environmental authority application or amendment documents | Environment | Department of the Environment, Tourism, Science and Innovation, Queensland (detsi.qld.gov.au).
Copies of, or extracts from, the application documents may also be obtained at rcooper@savannahgoldfields.com
It is advised that any person may make a submission about the application documents during the submission period, which is from 11/06/2026 to 8/07/2026. Submission must be received on or before 4.30pm on the last day of the submission period. Submissions must be sent to:
Department of the Environment, Tourism, Science and Innovation
Minerals and Northern Compliance, Environmental Services and Regulation
PO Box 7230 Cairns QLD 4870
ESCairns@detsi.qld.gov.au
Attention: Mineral Business Centre
The Department of the Environment, Tourism, Science and Innovation as administering authority shall accept all properly made submissions and may accept written submissions even if they are not properly made. A properly made submission must meet all of the following requirements:
- be written or made electronically
- state the name and address of each submitter
- be made to the administering authority stated above
- be received on or before the last day of the submission period
- state the grounds of the submission and the facts and circumstances relied on in support of the grounds.
Submission may be made using the Submission form: Application or amendment application for an environmental authority / PRC plan / PRCP schedule (ESR/2015/1617). If you wish to make submissions electronically, please use submission form (ESR/2015/1617) as a guide about the matters that are to be included.
Enquiries about the application can be made directly to:
Department of the Environment, Tourism, Science and Innovation
PO Box 7230 Cairns QLD 4870